Design and Construction of Integral Lifting Platform for Tianjin CTF Financial Center Project
In the tower core tube construction process of Tianjin CTF Financial Center project,the project uses the integral lifting platform,fully considers the characteristics,difficulties and needs in design process of the integral lifting platform.Through the detailed analysis and a large number of analysis and contrasting bold innovation,the multi-directional flexible and multi-dimensional adjustable high security and high level platform design and safe and efficient construction are achieved.It effectively solves the problems of changeable plan and elevation of the project,many restrictions,tight duration and high safety requirements.Without affecting the construction of the main body to complete the platform 5 times,this project created 2.5 days/floor construction speed record of the fastest core tube structure in China.