首页|盾构通过后隧道风井暗挖施工技术研究

盾构通过后隧道风井暗挖施工技术研究

扫码查看
北京地铁 17 号线区间隧道采用盾构先行通过后横向暗挖风道的施工工艺,上层风道跨越盾构隧道开挖至端墙,下层风道开挖临近至盾构隧道.在上层风道二衬结构保护下,采用倒挂井壁法开挖盾构隧道两侧土体,施工竖井二衬,保留盾构隧道范围内的下层风道侧墙及底板不施工,以保证后期施工安全.通过风道中板预留吊装孔,对管片逐环拆除,然后施工盾构隧道范围内的下层风道侧墙及底板.风道横向暗挖之前,为防止盾构隧道变形,减小地表沉降,需先对风道范围之外的管片采取径向注浆、纵向拉紧、设置环向支撑等加固措施.因需要进行多次受力转换,采用荷载-结构法对二衬结构进行各阶段内力分析.采用地层-结构法对开挖风道、竖井、拆除管片进行各阶段变形及应力分析,结果表明,地表沉降满足要求.监测结果反映地表沉降达到 99.1mm,主要原因为竖井开挖到底后,因遇到承压水,未及时封底,导致支护结构无法闭合成环形成整体受力体系,竖井底部土体无法对底板提供支撑,导致地表沉降超标.
Tunnel Air Shaft Excavation Technology After Shield Tunnelling
The interval tunnel of Beijing Metro Line 17 adopted the construction technology of a shield first passing through and then transversely excavating the air duct.The upper air duct was excavated across the shield tunnel to the end wall,and the lower air duct was excavated adjacent to the shield tunnel.Under the protection of the secondary lining structure of the upper air duct,the soil on both sides of the shield tunnel was excavated by the inverted shaft wall,the secondary lining of the shaft was constructed,and the side wall and bottom plate of the lower air duct within the scope of the shield tunnel were not constructed to ensure the safety of the later construction.The hoisting holes were reserved through the middle plate of the air duct,the segments were removed ring by ring,and then the side wall and bottom plate of the lower air duct within the scope of the shield tunnel were constructed.Before the horizontal excavation of the air duct,it was necessary to take reinforcement measures such as radial grouting,longitudinal tension and circumferential support for the segments outside the air duct to prevent the deformation of the shield tunnel and reduce the surface settlement.Due to the need for multiple force conversions,the load-structure method was used to analyze the internal force of the secondary lining structure at each stage.The stratum-structure method was used to analyze the deformation and stress of each stage of excavation for air duct,shaft and segment demolition.The results show that the surface settlement meets the requirements.The monitoring results show that the surface subsidence reaches 9.91cm.The main reason is that after the shaft is excavated to the end,the supporting structure cannot be closed into a ring to form an overall force system due to the confined water and the failure to seal the bottom in time,resulting in the surface settlement exceeding the standard.

subwaystunnelsshieldsair ductreinforcementsettlement

叶家强、丁静泽

展开 >

北京市市政工程设计研究总院有限公司,北京 100082

地铁 隧道 盾构 风道 加固 沉降

北京市市政工程设计研究总院有限公司课题

2023-ZCTD-04

2024

施工技术(中英文)
亚太建设科技信息研究院 中国建筑设计研究院 中国建筑工程总公司 中国土木工程学会

施工技术(中英文)

影响因子:1.244
ISSN:2097-0897
年,卷(期):2024.53(1)
  • 1
  • 3