首页|澄清池出水浊度超标问题分析和解决措施

澄清池出水浊度超标问题分析和解决措施

扫码查看
邹县发电厂针对 1000 MW火电机组中水处理单元澄清池存在的出水浊度超标问题,进行原因分析和要因确认,分析得出造成澄清池出水浊度超标的主要原因是脱水机运行参数不合理、脱水机处理量达不到系统要求.通过调整运行参数、降低污泥外排污泥量,实现了澄清池出水浊度均小于 10 NTU,出水浊度满足达标排放要求.
Analysis and Solution Measures for the Problem of Turbidity Exceeding the Standard in the Effluent of the Clarification Tank
Zouxian Power Plant conducted a root cause analysis and confirmation of the issue of excessive turbidity in the effluent of the clarification tank of the water treatment unit in a 1 000 MW thermal power unit.The main reasons for the excessive turbidity in the effluent of the clarification tank were found to be the unreasonable operating parameters of the dewatering machine and the insufficient processing capacity of the dewatering machine to meet the system requirements.By adjusting operating parameters and reducing the amount of sludge discharged externally,the turbidity of the effluent from the clarification tank was achieved to be less than 10 NTU,and the effluent turbidity met the standard discharge requirements.

sewage treatmentpower plantclarifying tankeffluent turbidity

陈中阳

展开 >

华电国际邹县发电厂,山东 邹城 273500

污水处理 电厂 澄清池,出水浊度

2024

山西化工
山西省煤化工发展促进中心 山西省化工学会

山西化工

影响因子:0.293
ISSN:1004-7050
年,卷(期):2024.44(10)