摘要

以某钢厂烧结项目SHRT系统建设中BIM技术的应用为例,分析了SHRT系统的技术特点,从数字化P&ID、协同设计等方面对BIM技术在实际工程中的应用价值进行了研究.应用实践表明,BIM技术的应用可提高设计效率,且能带来显著的经济和环保效益.

Abstract

This paper takes the application of BIM technology in the construction of SHRT system of a steel plant sintering project as an example,analyzes the technical characteristics of the SHRT system,and studied on the application value of BIM technology in practical engineering from aspects such as digital P&ID and collaborative design.Application practice has shown that the application of BIM technology can improve design efficiency and bring significant economic and environmental benefits.

关键词

余热利用/SHRT/BIM/协同设计

Key words

waste heat utilization/SHRT/BIM/collaborative design