Practice of Opening a Large Blast Furnace in the South
This article mainly summarizes the start-up work of a newly built large blast furnace in China.Before the furnace was opened,due to the incomplete powder making system,full coke smelting continued after the furnace was opened,affecting the process of reaching production.Through scientific calculation of the start-up material and precise adjustment during the start-up process,it took 42 hours to gradually stabilize various operating parameters of the blast furnace,achieving the goal of safe start-up.