为解决新景矿15124工作面瓦斯超限问题,基于"O"形圈理论和瓦斯抽采机制,提出工作面定向长钻孔瓦斯治理技术,并根据现场实际情况确定了定向长钻孔技术参数,现场实践结果表明:采用定向长钻孔瓦斯治理技术,单孔最大瓦斯纯流量达到10.1%、瓦斯浓度达到0.2m3/min,有效保证了井下工作面的安全回采.
Research on Gas Control Technology for High Altitude Directional Long Drilling of Roof
In order to solve the problem of gas exceeding the limit in the 15124 working face of Xinjing Mine,based on the"O"ring theory and gas extraction mechanism,a directional long drilling gas treatment technology for the working face is proposed.The parameters of the directional long drilling technology are determined according to the actual situation on site.The on-site practice results show that using the directional long drilling gas treatment technology,the maximum pure gas flow rate of a single hole reaches 10.1%,and the gas concentration reaches 0.2 m3/min,effectively ensuring the safe recovery of the underground working face.

working facegas exceeding limitdirectional long drillingtechnical parameter

王钰剑

展开 >

山西新景矿煤业有限责任公司,山西 阳泉 045000

工作面 瓦斯超限 定向长钻孔 技术参数

2024

山西冶金
山西省金属学会 山西省有色金属学会

山西冶金

影响因子:0.139
ISSN:1672-1152
年,卷(期):2024.47(6)