首页|半煤岩巷快速掘进综合除尘技术

半煤岩巷快速掘进综合除尘技术

扫码查看
陕北矿业有限公司韩家湾煤矿井下半煤岩巷快速掘进过程粉尘浓度较大,已严重影响作业人员身体健康,制约矿井高产高效生产安全.通过分析半煤岩掘进巷道除尘能力水平,发现掘进工作面粉尘颗粒细且多为岩尘,现有的通风除尘设备无法及时排出.通过优化除尘设备,采用长压短抽综合除尘技术,数值模拟分析得出其除尘效率高,能进一步降低粉尘浓度,掘进头粉尘浓度降至5 mg/m3以下,满足矿井安全生产需求.该技术为矿井掘进工作面质量标准化作业以及施工环境安全提升奠定坚实基础,具有显著的经济与社会效益.
Comprehensive dust removal technology for rapid tunneling in semi-coal rock roadway
The dust concentration is high during the rapid tunneling process of underground semi-coal rock roadway in the Hanjiawan coal mine,severely affecting the physical health of the workers and hindering the improvement of high productivi-ty and efficiency.Through analyzing the dust removal capability level in semi-coal rock tunneling,we find that the dust parti-cles in the tunneling face are fine and mostly rock dust,and the existing ventilation dust removal equipment cannot remove the dust in time.By optimizing the dust removal equipment and adopting the comprehensive dust removal technology of long-pressurization and short-extraction,numerical simulation analysis shows that the dust removal efficiency is high and can fur-ther reduce the dust concentration.The dust concentration at the tunneling face is reduced to below 5 mg/m3,which is satis-factory for the mine safety requirement.The technology lays a solid foundation for improving the quality of tunneling work and the safety of construction environment in tunneling face,and has significant economic and social benefits.

semi-coal rock roadwaylong pressure short extractionnumerical simulationcomprehensive dust removal

李慧刚、田世雄、周竹峰、卢少帅

展开 >

陕西陕北矿业韩家湾煤炭有限公司,陕西榆林 719315

半煤岩巷 长压短抽 数值模拟 综合除尘

2024

陕西煤炭
陕西省煤炭工业协会 神华神东煤炭集团有限责任公司 陕西煤业化工集团有限责任公司

陕西煤炭

影响因子:0.204
ISSN:1671-749X
年,卷(期):2024.43(9)