陕西水利2024,Issue(8) :125-127,131.

郎溪县第一联合圩堤防防渗加固措施研究

Study on Anti-seepage Reinforcement Measures of the First Joint Dike in Langxi County

张仲伯
陕西水利2024,Issue(8) :125-127,131.

郎溪县第一联合圩堤防防渗加固措施研究

Study on Anti-seepage Reinforcement Measures of the First Joint Dike in Langxi County

张仲伯1
扫码查看

作者信息

  • 1. 连云港市水利规划设计院有限公司合肥分公司,安徽合肥 230000
  • 折叠

摘要

为提高郎溪县第一联合圩工程的安全性,对堤防进行防渗加固.结合工程实际情况,对堤身、堤基防渗加固方案进行分析.经过方案比选,堤身选用多头小直径搅拌桩方案进行防渗加固;堤基采用填塘固基防渗方案.经过分析计算,加固后堤防的安全性显著提升,可为类似工程提供参考.

Abstract

In order to improve the safety of the first joint polder project in Langxi County,the embankment is reinforced.Combined with the actual situation of the project,the anti-seepage reinforcement scheme of the embankment body and foundation is analyzed.After scheme comparison and selection,the dike body adopts multi-head small-diameter mixing pile scheme for anti-seepage reinforcement;the embankment foundation adopts the anti-seepage scheme of filling pond and solid foundation.After analysis and calculation,the safety of the embankment after reinforcement is significantly improved,which can provide reference for similar projectsl.

关键词

堤防/防渗/加固/稳定性

Key words

Embankment/anti-seepage/reinforcement/stability

引用本文复制引用

出版年

2024
陕西水利
陕西省城乡供水管理办公室

陕西水利

影响因子:0.185
ISSN:1673-9000
参考文献量2
段落导航相关论文