石家庄铁路职业技术学院学报2024,Vol.23Issue(2) :62-66.

山岭隧道近阶下穿高压电塔施工方案及电塔变形规律研究

Research on the Construction Plan and Tower Deformation Rule of High Voltage Electric Towers Underpass the Mountain Tunnel

齐同晓
石家庄铁路职业技术学院学报2024,Vol.23Issue(2) :62-66.

山岭隧道近阶下穿高压电塔施工方案及电塔变形规律研究

Research on the Construction Plan and Tower Deformation Rule of High Voltage Electric Towers Underpass the Mountain Tunnel

齐同晓1
扫码查看

作者信息

  • 1. 中铁十八局集团第四工程有限公司,天津,300350
  • 折叠

摘要

隧道近阶下穿对既有构筑物产生扰动,威胁既有构筑物的安全运营.根据具体工程案例,提出隧道下穿高压电塔施工方案,并揭示高压电塔的水平位移和竖向沉降规律.研究成果为隧道下穿工程提供参考,保障隧道上方临近结构的安全.

Abstract

When an existing structure is underpassed by a tunnel at close range,the structure will be disturbed and its safety operation will be threatened.Based on specific engineering case,tunnel construction measurements are proposed when high voltage towers are underpassed.At the same time,rules of horizontal displacement and vertical settlement of the towers are revealed.The research results can provide references for tunnel underpassing engineering and ensure the safety of adjacent structures above the tunnel.

关键词

隧道/下穿/高压电塔/水平位移/沉降

Key words

Tunnel/Underpass/High Voltage Tower/Horizontal Displacement/Settlement