The"continuous peeling"method is mainly used in pipe jacking construction without receiving shafts,where waterproofing is challenging,deformation control demands are high,and concrete pouring efficiency is low.Based on the"continuous peeling"pipe jacking reception project at Exit 3 of Shenmei Road Station on Shanghai Metro Line 18,this paper addresses problems such as narrow construction space,difficulties in concrete pouring,waterproofing at joints,and tight construction schedules.It proposes construction techniques,such as using partitioned steel plates for casting within the pipe jacking machine's shell framework and setting up guided waterproof and drainage joints.These measures effectively solved the related construction issues and were successfully applied.This method can provide valuable reference for"continuous peeling"pipe jacking reception construction.
pipe jacking constructioncontinuous peelingreception construction technologyshell abandonmentguided waterproof joints