石台抽水蓄能电站施工供电系统设计

扫码查看
抽水蓄能电站施工供电系统建设除具有一般水电工程的特点,如场内建筑物布置分散、施工工期长、用电负荷大、站址位置偏僻、电源匮乏距离远等,通常还需考虑与未来电站运行期用电相结合,以最大限度利用施工期供电设施,减小重复建设.以石台抽水蓄能电站施工供电系统设计为例,介绍施工供电电源选择、供电设施永临结合设计方案,为今后类似工程应用提供借鉴和参考.
The Design of Construction Power Supply System for Shitai Pumped Storage Power Station
The construction of the power supply system for pumped storage power stations not only has the characteristics of general hydropower projects,such as scattered buliding layout,long construction period,large power load,remote station location,and the power shortage.However,the power supply system for pumped storage power stations also needs to be combined with future power supply during the operation period of the power station to maximize the utilization of power supply facilities during the construction period and reduce duplicate construction investment.This article focuses on the design of the construction power supply system for the Shitai pumped storage power station as an example to introduce the selection of construction power supply sources and the design of permanent and temporary power supply facilities,providing reference and guidance for similar engineering applications in the future.

pumped storage power stationconstruction periodpower supply designpermanent temporary union

汪威、潘少华、罗立哲、陈曦

展开 >

长江勘测规划设计研究有限责任公司,武汉 430010

抽水蓄能电站 施工期 供电设计 永临结合

2024

水利水电工程设计
中水北方勘测设计研究有限责任公司 天津市水力发电工程学会

水利水电工程设计

影响因子:0.209
ISSN:1007-6980
年,卷(期):2024.43(3)