摘要

输电线路全过程机械化施工,不仅减少了作业人员劳动强度,减少了施工占地,提升了施工效率,而且降低了输电线路施工各阶段的不安全风险,全面提升了现场施工安全水平.从高压输电线路施工的各阶段,详细介绍了机械化施工的应用,并从技术和经济、施工质量和安全性等方面对比分析了传统施工方法和机械化施工方法的差异,阐述了机械化施工方法的优势,为高压输电线路全过程机械化施工的应用提供了借鉴.

Abstract

The whole process mechanized construction of transmission lines not only reduces the labor intensity of operators,construction occupation,and improves the construction efficiency,but also reduces the risk of insecurity in all stages of transmission line construction.Thus,the safety level of site construction is comprehensively improved.At all stages of construction of high-voltage transmission lines,the application of mechanized construction is introduced in detail.The traditional construction method and mecha-nized construction method are compared and analyzed from the aspects of technology and economy,construction quality and safety,and the advantages of mechanized construction method are described,which provides reference for the application of the whole process mechanized construction of high-voltage transmission lines.

关键词

输电线路/机械化施工/施工效率/施工安全

Key words

transmission lines/mechanized construction/construction efficiency/construction safety