综放工作面停采线位置确定及聚酯纤维柔性网应用

扫码查看
为确保 3308 综放工作面末采期间围岩稳定,借助数值模拟、理论分析的方法确定停采煤柱合理宽度,最终设计停采线煤柱宽度不小于 49 m.为降低工人劳动强度,利用金属网配合柔性网护顶的方法,实现了工作面安全快速回撤,提高了护顶效果,降低了劳动强度,缩短了末采周期,节约了支护成本,对类似条件综放工作面的高效回撤提供了有效借鉴.
Location of Stopping Line and Application of Polyester Fibre Flexible Mesh in Fully-mechanized Caving Face
In order to ensure the stability of the surrounding rock during the final mining of 3308 fully-mechanized caving face,the reasonable size of the stop mining coal pillar was determined with the help of numerical simulation and theoretical analysis,and the final design of the width of the stopping line coal pillars needs to be more than 49 m.In order to reduce the labor intensity of workers,the method of metal mesh combined with flexible mesh to protect the roof of the working face was used to realize safe and rapid withdrawal of the working face,improve the effect of roof protection,reduce the labor intensity,shorten the final mining period and save the support cost,which can provide an effective reference for the efficient withdrawal of the full-mechanized caving working face under similar conditions.

flexible meshstopping lineadvanced supporting pressurewithdrawal

谭浩、魏宝贞、顾锋、李宁、李文林

展开 >

兖矿能源集团股份有限公司东滩煤矿,山东 邹城 273500

柔性网 停采线 超前支承压力 回撤

2024

能源与节能
山西省能源研究会 山西省节能研究会

能源与节能

影响因子:0.561
ISSN:2095-0802
年,卷(期):2024.(1)
  • 9