首页|煤矿工作面掘进巷道断层支护方案设计及优化

煤矿工作面掘进巷道断层支护方案设计及优化

扫码查看
主要针对煤矿工作面掘进巷道断层支护方案优化进行研究.首先,概述了巷道断层形成的原因及方法的确定,其次,以一煤矿13102 工作面为例,详细描述了巷道断层原支护设计的应用情况,并对支护不足进行了分析,提出了针对临时支护和永久支护的优化方案,并探讨了支护优化后的应用效果.结果显示断层区围岩应力显现现象得到明显改善,保障了巷道掘进安全.
Design and Optimization of Fault Support Scheme for Coal Mining Face Excavation Roadways
This paper mainly focused on the optimization of fault support schemes for coal mining face excavation roadways.Firstly,it provided an overview of the causes and methods for the formation of roadway faults.Secondly,taking 13102 working face of a coal mine as an example,it provided a detailed description of the application of the original support design for roadway faults,analyzed the insufficient support,proposed optimization plans for temporary and permanent support,and explored the application effects of optimized support.The results show that the phenomenon of stress manifestation in the surrounding rock of the fault area has been significantly improved,ensuring the safety of tunnel excavation.

coal mining faceexcavation roadwayfault supportdesign optimization

赵春阳

展开 >

山西省煤炭建设监理有限公司,山西太原 030000

煤矿工作面 掘进巷道 断层支护 设计优化

2024

能源与节能
山西省能源研究会 山西省节能研究会

能源与节能

影响因子:0.561
ISSN:2095-0802
年,卷(期):2024.(4)