摘要

论述了晋中供水有限责任公司东山水源地供水管线穿越潇河沉管工程的施工方案,采用沉管的施工方法有效地解决了该项目施工场地限制的问题,减少了河槽大开挖及河道导流的工程量,充分体现了沉管法施工的优势.对沉管法施工工艺进行了介绍,对其技术要点进行了详细介绍.

Abstract

The immersed tube construction scheme of the water supply pipeline in Dongshan water source area crossing the Xiaohe River,which belongs to Jinzhong Water Supply Co.,Ltd.,was discussed.The immersed tube method effectively solved the problem of limited construction site for the project,reduced the amount of large-scale excavation and river diversion work,and fully reflected the advantages of the immersed tube method construction.The construction process of the immersed tube method was introduced.A detailed introduction was given to the technical points of the immersed tube method construction.

关键词

沉管施工/支护桩打拔/水下沟槽开挖/水下回填

Key words

immersed tube construction/driving and pulling of support piles/underwater trench excavation/un-derwater backfilling