铁路隧道预留变形收敛对于混凝土超耗的定量关系研究
Study on the Quantitative Relation of Reserved Deformation Convergence of Railway Tunnel for Concrete Overconsumption
周中 1马跃龙 2袁东3
作者信息
- 1. 中铁五局集团有限公司,长沙 410000
- 2. 中国中铁股份有限公司工程经济研究院,北京 100000
- 3. 中铁二局集团有限公司,成都 610000
- 折叠
摘要
铁路隧道混凝土超耗受诸多因素影响,预留变形收敛是主要原因之一.本文通过大量的样本隧道,分别采用监控量测数据分析法和三维激光扫描仪实测法计算分析钻爆法施工隧道预留变形量和收敛值,揭示在正常施工条件下预留变形收敛对于混凝土超耗的定量关系,提出相应措施,为钻爆法施工隧道混凝土超耗控制提供借鉴.
Abstract
The excessive consumption of railway tunnel concrete is affected by many factors,and the reserved deformation convergence is one of the main reasons.Through a large number of sample tunnel,monitoring measuring data analysis and 3 d laser scanner measurement method calculation and analysis drilling blasting tunnel reserved deformation and convergence value,reveals the normal construction conditions reserved deformation convergence for concrete excessive quantitative relationship,put forward the corresponding measures,for drilling blasting tunnel concrete excessive consumption control.
关键词
铁路隧道/预留变形收敛/混凝土超耗/影响程度Key words
railway tunnel/allow deformation convergence/concrete over consumption/influence degree引用本文复制引用
出版年
2024