首页|浅层超稠油油藏双水平井SAGD电加热预热启动参数优化设计与矿场试验

浅层超稠油油藏双水平井SAGD电加热预热启动参数优化设计与矿场试验

扫码查看
由于新疆油田陆相非均质超稠油油藏SAGD注蒸汽循环预热启动过程中,注采井井间压差波动较大,现场调控难度大,蒸汽易进入高渗透水平段油层,造成水平段局部优先连通或者汽窜,蒸汽腔发育不均衡,导致水平段动用程度较低,从而影响SAGD生产效果.为此,提出了双水平井SAGD水平段下入电加热器的开发方式,利用热传导原理对注采井井间的油层进行均匀加热,并优化了SAGD电加热预热启动的关键操作参数,包括SAGD电加热启动井筒预处理、流体替液循环操作参数和转SAGD生产时机,形成了SAGD电加热预热启动操作流程.在新疆油田重A井区FHW01TW井组浅层超稠油双水平井进行SAGD电加热预热启动矿场试验,预热启动时间从 320 d下降至 163 d,节省蒸汽 3.79×104 t,减少CO2 排放 4 846.6 t.该技术将成为双水平井SAGD开发降低CO2 排放的重要手段之一.
Optimization Design and Field Test of SAGD Electric Heating Preheating Start-up Parameters for Double Horizontal Wells in Shallow Super-Heavy Oil Reservoirs
Due to the large fluctuation of pressure difference between injection and production wells during the pre-heating and start-up process of SAGD steam injection cycle in continental heterogeneous ultra-heavy oil reservoirs in Xinjiang Oilfield,it is difficult to control on site.Steam is easy to enter the oil layer of high permeability horizon-tal section,which is easy to cause local preferential connection or steam channeling in horizontal section.The devel-opment of steam chamber is not balanced,which leads to the low utilization degree of horizontal section,thus affect-ing the production effect of SAGD.Therefore,the development method of putting electric heaters into the horizontal section of SAGD in double horizontal wells is proposed.The oil layer between injection and production wells is uni-formly heated by the principle of heat conduction,and the key operation parameters of SAGD electric heating pre-heating start-up are optimized,including SAGD electric heating start-up wellbore pretreatment,fluid replacement cycle operation parameters and SAGD production time.The SAGD electric heating preheating start-up operation process is formed.SAGD electric heating preheating start-up field test was carried out in the shallow ultra-heavy oil double horizontal well of FHW01TW Well Group in Chong A Well Area of Xinjiang Oilfield.The preheating startup time was reduced from 320 days to 163 days,3.79×104 t steam was saved and 4 846.6 t CO2 emission was re-duced.This technology will become one of the important means to reduce CO2 emission in SAGD development of shallow double horizontal wells.

SAGDelectrical heatingpreheating start-upsuper-heavy oilXinjiang Oilfield

何万军、孙新革、吴永彬、罗池辉、郭昊、张基朋、李淑娴

展开 >

中国石油新疆油田分公司,新疆 克拉玛依 834000

中国石油勘探开发研究院,北京 100083

中国地质大学(北京),北京 100083

SAGD 电加热 预热启动 超稠油 新疆油田

2024

特种油气藏
中油辽河油田公司

特种油气藏

CSTPCD北大核心
影响因子:1.626
ISSN:1006-6535
年,卷(期):2024.31(6)