基于EWM-GRA综合评价的采场结构参数优化研究

扫码查看
为实现某地下磷矿增产目标,在综合考虑采矿安全、技术和经济因素下,结合EWM熵权法和GRA灰关联度法构建了EWM-GRA综合评价模型,并基于评价模型对9组不同采场结构参数方案进行分析.研究结果表明:选择采用进路宽度为3.5 m,进路高度为3m的方案最优.从现场实践来看,采用3.5 m×3 m采场结构参数方案相对原方案采矿量每米整体提高了27.37%,可实现增产目标;每条进路的经济效益相对原方案增加了2.833万元,大于增加的开采成本,说明了优选出的采场结构参数方案是合理可行的.研究结果可为磷矿采场结构参数设计提供参考.
Study on Optimization of Stope Structure Parameters Based on EWM-GRA Comprehensive Evaluation
In order to achieve the goal of increasing production of an underground phosphate rock,the EWM-GRA comprehensive evaluation model was constructed by combining the EWM entropy weight meth-od and the GRA grey correlation method under the comprehensive consideration of mining safety,technical and economic factors.Based on the evaluation model,nine groups of different stope structure parameter schemes were analyzed.The results show that the scheme with the route width of 3.5 m and the route height of 3 m is the best.From the field practice,the mining volume per meter of the 3.5 m×3 m stope structure parameter scheme is 27.37%higher than that of the original design scheme,which can achieve the goal of increasing production.Compared with the original scheme,the economic benefit of each approach has in-creased by 28.33 thousand yuan,which is greater than the increased mining cost,indicating that the opti-mized stope structure parameter scheme is reasonable and feasible.The research results can provide refer-ence for the design of structural parameters of phosphate mine stope.

stope structure parametersEWM entropy weight methodEWM-GRA comprehensive evaluation model

杨志刚、周帆、张佳男、董健、郑魁、袁明礼、唐志书、尹裕

展开 >

云南磷化集团有限公司

国家磷资源开发利用工程技术研究中心

南华大学核资源与安全工程学院

中钢集团马鞍山矿山研究总院股份有限公司

展开 >

采场结构参数 EWM熵权法 EWM-GRA综合评价模型

2024

现代矿业
中钢集团马鞍山矿山研究院有限公司

现代矿业

影响因子:0.33
ISSN:1674-6082
年,卷(期):2024.40(4)
  • 16