首页|某磷矿立井井筒掘进防治水优化分析

某磷矿立井井筒掘进防治水优化分析

扫码查看
某大型磷矿立井井筒掘进过程中遇灯影组白云岩含水层,存在水文地质条件复杂、涌水量大、井筒建设施工困难等问题.采用地面、工作面预注浆,对井筒浇注接茬处细小水点采用壁后注浆综合治理措施;采用现场注浆试验,对注浆工艺参数进行优化研究,从+616 m工作面开始调整孔间距、钻孔角度,将钻孔数量由21个调整为23个,同时将开孔角度调整为4°,调整后开孔间距0.74 m,终孔间距2.13 m,落孔圈径14.966 m.结果表明,一序孔单孔注浆量更大,二序孔涌水量降低了82%;对细小裂隙进行封堵,减小工作面涌水量,改善工作面作业环境,获得了较好的注浆堵水效果,为类似大水矿山提供参考.
Optimization Analysis of Water Control in Shaft Excavation of a Phosphate Mine
In the process of shaft excavation of a large phosphate mine,Dengying formation dolomite aquifer is encountered,which has complicated hydrogeological conditions,large water inflow and difficul-ties in shaft construction.Pre-grouting of the surface and the working face are adopted,the comprehensive treatment measures of the grouting after the small water point wall at the casting joint of the shaft are taken.The field grouting test is used to optimize the grouting process parameters.The hole spacing and drilling an-gle are adjusted from+616 m working face,and the number of holes is adjusted from 21 to 23.At the same time,the opening angle is adjusted to 4°,the opening distance is 0.74 m after adjustment,the final hole dis-tance is 2.13 m,and the hole drop ring diameter is 14.966 m.The results show that the grouting volume of the first sequence hole is larger,and the water inflow of the second sequence hole is reduced by 82%.The small cracks are blocked,the water gushing of the working face are reduced,the working environment of the working face is improved,and the better water plugging effect is obtained,which provides a reference for similar large water mines.

phosphate mineshaft excavationpre-grouting of the surfacepre-grouting of the work-ing face

冯冬、赵青、杨胜贤

展开 >

四川省先进材料产业投资集团有限公司

瓮安县天一矿业有限公司

磷矿 立井井筒掘进 地面预注浆 工作面预注浆

2024

现代矿业
中钢集团马鞍山矿山研究院有限公司

现代矿业

影响因子:0.33
ISSN:1674-6082
年,卷(期):2024.40(5)