首页|预制整体式弧形件施工质量控制指标研究

预制整体式弧形件施工质量控制指标研究

扫码查看
预制整体式弧形件的施工质量是大直径盾构隧道施工中的关键,需要针对预制整体式弧形件施工质量提出有效合理的控制指标.鉴于此,对现有工程中预制轨下结构或箱涵的施工质量控制指标进行总结,阐述预制整体式弧形件构造及施工流程,提出预制整体式弧形件的施工质量控制指标,并进行现场实践.结果表明,按照提出的指标进行施工的弧形件,施工效率高、质量好,应用效果良好.
Study on Construction Quality Control Criteria for Prefabricated Integrated Arcuate Members
The construction quality of prefabricated integrated arcuate members is a key element in construction of large-diameter shield tunnel,so it is necessary to establish effective and rational control criteria for the construction quality of prefabricated integrated arcuate members.In light of this,the construction quality control criteria for the prefabricated sub-rail structure or box culvert of the existing projects are reviewed,the composition and construc-tion process of prefabricated integrated arcuate members are explained,the construction quality control criteria for prefabricated integrated arcuate members are proposed,and the criteria are practiced in actual works.As the results indicate,construction of the arcuate members that are built under the criteria proposed has high efficiency and good quality,and the members perform well in service.

Large-diameter shield tunnelPrefabricated arcuate memberConstruction qualityControl criteria

郝鹏飞

展开 >

中铁十四局集团大盾构工程有限公司,南京 211800

大直径盾构隧道 全预制弧形件 施工质量 控制指标

中铁十四局集团有限公司科研课题

202214jtky0069

2024

现代隧道技术
中铁西南科学研究院有限公司 中国土木工程学会隧道及地下工程分会

现代隧道技术

CSTPCD北大核心
影响因子:1.493
ISSN:1009-6582
年,卷(期):2024.61(1)
  • 15