乐西高速大凉山1号隧道地质条件复杂、气候条件恶劣,受自然保护区限制选线困难.文章提出最大限度降低越岭高程的设计思路,以保障运营安全.通过设置贯通平导、选择隧道掘进机法与钻爆法组合的施工工法、优化隧道通风方案,解决超特长隧道施工工期、防灾救援等难题,降低了施工风险,提高了防灾救援效率,项目总体功能和施工运营安全性达到较优.通过项目实施及研究表明,超特长隧道采用主线隧道+贯通平导的建设方案是可行的,对于西部山区超特长高速公路隧道的建设具有一定的借鉴意义.
Key Technologies for Design and Construction of the Daliangshan No.1 Tunnel
The geological conditions of the Daliangshan No.1 Tunnel on the Leshan-Xichang Expressway are com-plex,and the climate conditions are harsh,making it difficult to select the road alignment due to restrictions from the nature reserves.This paper proposes a design concept to minimize the elevation of the ridge crossing section to ensure operational safety.By setting up a fulllength parallel heading,selecting a combination of tunnel boring ma-chine(TBM)method and drilling and blasting method for construction,and optimizing the tunnel ventilation scheme,the challenges regarding construction period and disaster prevention and rescue of the ultra-long tunnel are addressed,reducing construction risks and improving disaster rescue efficiency.The overall function,the construc-tion and operation safety of the Project are optimized.The relevant research and implementation of the Project show that the construction scheme of the main tunnel + full-length parallel heading for ultra-long tunnels is feasible and has certain reference significance for the construction of ultra-long expressway tunnels in western mountainous areas.

Overall designExtra-long tunnelFull-length parallel headingOpen TBMEquipment modification

李玉文、蔚艳庆

展开 >

四川省公路规划勘察设计研究院有限公司,成都 610041

总体设计 特长隧道 贯通平导 敞开式掘进机 设备改造