在役岩溶隧道衬砌承受的水压与排水设计方案密切相关.以渝昆高铁中梁山隧道为依托工程,在山岭隧道通用排水设计方案的基础上设计3种改进的排水方案,将岩溶地层等效为均质渗流地层,采用三维数值模拟方法研究3种排水方案条件下隧道衬砌水压分布规律,并对岩溶隧道衬砌水压进行实测.结果表明:(1)对于岩溶弱发育隧道,正常排水时,隧道衬砌拱顶及拱腰水压可大幅度折减,但是隧道衬砌边墙、墙脚及仰拱仍然承受水压;(2)沿隧道纵向,衬砌各测线的水压均呈"M"型分布,在环向排水管处水压最低,在两个环向排水盲管之间的水压较高;(3)在隧道横断面衬砌仰拱水压折减效果方面,中心水沟落底的效果最好,其次是仰拱增加泄水孔及三通管方案,仅在仰拱增加三通管的方案排水效果最差;(4)综合考虑水压折减效果及施工质量,推荐中梁山隧道岩溶弱发育段采用仰拱设环向排水盲管同时在仰拱和墙脚增加泄水孔方案;(5)衬砌仰拱水压监测结果显示,受地表降雨影响岩溶隧道衬砌水压具有明显的波动性,实测仰拱水压及分布与数值模拟结果接近,验证了推荐排水方案的有效性.
Study on Drainage Schemes for Karst Tunnels Based on Hydraulic Pressure Characteristics
The water pressure on the lining of in-service karst tunnels is closely related to the drainage design scheme.Based on the Zhongliangshan Tunnel on the Chongqing-Kunming High-Speed Railway,three improved drainage schemes were designed on the basis of the general drainage design scheme for mountain tunnels.Treating the karst strata as equivalent homogeneous seepage strata,a three-dimensional numerical simulation was conducted to analyze the water pressure distribution patterns on tunnel lining under the three schemes.Field measurements of water pressure were also performed.The results reveal the following:(1)For weakly developed karst tunnels,under normal drainage conditions,water pressure at the crown and haunch of the tunnel lining can be significantly re-duced,but the sidewall,wall-foot,and invert arch still bear substantial water pressure;(2)Along the longitudinal di-rection of the tunnel,the water pressure on all measuring lines of the lining exhibits an"M"-shaped distribution,with the lowest pressure at the circumferential drainage pipes and higher pressure between two circumferential drainage blind pipes;(3)In terms of reducing water pressure on the invert arch,the scheme with a bottomed central drainage ditch is the most effective,followed by the scheme with additional dense drainage holes in the invert arch,while the scheme with only circumferential drainage blind pipes in the invert arch performs the worst;(4)Considering both water pressure reduction effectiveness and construction quality,it is recommended that the weakly developed karst sections of the Zhongliangshan Tunnel adopt a scheme with circumferential drainage blind pipes in the invert arch and additional drainage holes in the invert arch and wall-foot;(5)Monitoring results of water pressure on invert arch show significant fluctuations influenced by surface rainfall.The measured water pressure and distribution on in-vert arch closely match the numerical simulation results,validating the effectiveness of the recommended drainage scheme.

Karst tunnelDrainage schemeWater pressure distribution on liningWater pressure monitoring

赵东平、和琦、杜卿、张文

展开 >

西南交通大学土木工程学院,成都 610031

西南交通大学极端环境岩土和隧道工程智能建养全国重点实验室,成都 610031

中铁十一局集团有限公司,武汉 430061

岩溶隧道 排水方案 衬砌水压分布 水压监测

2024

现代隧道技术
中铁西南科学研究院有限公司 中国土木工程学会隧道及地下工程分会

现代隧道技术

CSTPCD北大核心
影响因子:1.493
ISSN:1009-6582
年,卷(期):2024.61(6)