基于组织-任务网络的项目进度风险分析

扫码查看
针对工程项目外部进度风险的传播与控制,构建项目组织-任务网络模型,依据级联失效理论,从风险荷载、节点容量、荷载重分配与失效判别规则四方面确定项目进度风险的传播机制.仿真结果表明,组织和任务间的相互关系会扩大外部风险对项目进度的影响,且随机组织失效造成的影响大于关键组织.通过增加风险投入、加强预警、提高容错率可在一定范围内增强项目风险抵抗能力,同时需要加强非关键组织的风险预警与管控,有效控制外部风险对项目进度造成的影响.
Analysis of project schedule risk based on organization-task network
This paper builds an organization-task network model to study the propagation effect and control of project external schedule risks.Project schedule risk propagation mechanism of the network model is deter-mined.The mechanism includes risk load,node capacity,load redistribution and failure discrimination rules according to cascading failure theory.Simulation results show that the organization-task interrelationship am-plifies the impacts of external risks.Meanwhile,random organizational failure causes a greater impact than critical organization in the presence of risk.Therefore,increasing risk investment,strengthening early warn-ing,and improving fault tolerance rate can enhance the risk resistance to a certain extent.Risk monitoring and control of non-critical organizations need to be strengthened to effectively control the impact of external risks on the project schedule.

organization-task networkrisk propagationcascading failureproject schedulemodeling and simulation

施骞、刘安谱、肖超

展开 >

同济大学经济与管理学院,上海 200092

组织-任务网络 风险传播 级联失效 项目进度 建模仿真

国家自然科学基金资助项目国家自然科学基金资助项目国家社会科学基金资助项目

72072131T226112947620CGL047

2024

系统工程学报
中国系统工程学会

系统工程学报

CSTPCD北大核心
影响因子:1.192
ISSN:1000-5781
年,卷(期):2024.39(4)