西南山区某浅埋铁路双线隧道主要穿越全风化、强风化玄武岩,在隧道支护过程中发生多次变形侵限,最大变形达 205 mm,给施工造成极大困难.为解决施工中存在的地表沉降、隧道变形及初期支护侵限问题,文章基于隧道支护结构的破坏特征,分析了隧道产生变形侵限的原因,确定隧道变形侵限段的临时支护形式,采用交叉中隔墙(CRD)法开挖,并采用隧道锚管径向注浆加固围岩、钢架支护等加强支护措施.通过实施以上技术方案,隧道顺利完成了对变形侵限的处理,并取得了较好的加固效果,可为类似隧道的施工处理提供借鉴和参考.
Research on Treatment Measures for Initial Support Deformation Invasion of a Shallow-buried Railway Tunnel in Southwestern Mountainous Areas
A shallow-buried railway double-track tunnel in southwestern mountainous areas mainly passes through fully-weathered and strongly-weathered basalt.During the tunnel support process,multiple deformation invasions occurred with the maximum deformation of 205 mm,which caused great difficulties to the construction.In order to solve the problems of surface subsidence,tunnel deformation and initial support invasion in construction,based on the failure characteristics of tunnel support structure,this paper analyzes the causes of tunnel deformation invasion,determines the temporary support form in tunnel deformation invasion section,adopts Cross Diaphragm(CRD)method to excavate,adopts tunnel anchor pipe radial grouting to reinforce surrounding rock,and adopts steel frame support and other support strengthening measures.Through the implementation of the above technical scheme,the tunnel successfully completed the treatment of deformation invasion,and achieved good reinforcement effect,which can provide reference for the construction treatment of similar tunnels.

shallow-buried tunnelinitial supportdeformation invasion

桂林岗、王唤龙

展开 >

云桂铁路云南有限责任公司,云南 昆明 650011

中铁二院工程集团有限责任公司,四川 成都 610031

浅埋隧道 初期支护 变形侵限

2024

工程技术研究
广州钢铁企业集团有限公司

工程技术研究

影响因子:0.081
ISSN:2096-2789
年,卷(期):2024.9(2)