文章基于经验总结法总结了道路桥梁施工中能应用预应力施工技术的场景,并通过案例分析法,探究富阳西站π型站台梁工程运用预应力施工技术进行结构临时加固的策略.经静载试验分析,确定加固效果良好.由此得出结论,预应力施工技术能满足道路桥梁工程施工中临时抗弯加固需求,在不影响工程正常通车的情况下实现安全、高效施工,相同工况下可以优先考虑预应力施工技术.
Application of Prestressed Construction Technology in Road and Bridge Construction
Based on the experience summary method,this article summarizes the scenarios where prestressed construction technology can be applied in road and bridge construction,and explores the strategy of using prestressed construction technology for temporary structural reinforcement in the π type platform beam project of Fuyang West Station through case analysis.After static load test analysis,it is determined that the reinforcement effect is good.From this,it can be concluded that prestressed construction technology can meet the temporary bending reinforcement requirements in road and bridge engineering construction,and achieve safe and efficient construction without affecting the normal operation of the project.Under the same working conditions,prestressed construction technology can be given priority consideration.

prestressed construction technologyroad and bridge constructionroad and bridge engineering

张官路

展开 >

中铁十二局集团第一工程有限公司,陕西 西安 710038

预应力施工技术 道路桥梁施工 道路桥梁工程

2024

工程技术研究
广州钢铁企业集团有限公司

工程技术研究

影响因子:0.081
ISSN:2096-2789
年,卷(期):2024.9(3)