工程技术研究2024,Vol.9Issue(4) :197-199.DOI:10.19537/j.cnki.2096-2789.2024.04.065

上海大管径排水管迁改及临时排水设计

Relocation and Temporary Drainage Design of Large-diameter Drainage Pipe in Shanghai

朱群淑
工程技术研究2024,Vol.9Issue(4) :197-199.DOI:10.19537/j.cnki.2096-2789.2024.04.065

上海大管径排水管迁改及临时排水设计

Relocation and Temporary Drainage Design of Large-diameter Drainage Pipe in Shanghai

朱群淑1
扫码查看

作者信息

  • 1. 上海锦兴市政设计咨询有限公司,上海 200125
  • 折叠

摘要

地下建筑物采用明挖施工时,若与大管径的排水管道管位相冲突,需要对大管径的排水管进行迁改,以保证排水通畅.文章以上海真如副中心地下公共车行通道工程为例,介绍了φ2700 mm的大管径排水管道的迁改方案,结合施工期间的临时排水设计,以比选出最经济合理的方案.

Abstract

When the underground building is constructed by open excavation,if it conflicts with the position of large-diameter drainage pipe,it is necessary to relocate the large-diameter drainage pipe to ensure smooth drainage.Taking the underground public vehicle passage project of Shanghai Zhenru Sub-center as an example,this paper introduces the relocation scheme of φ2700 mm large-diameter drainage pipeline,and combines the temporary drainage design during construction to select the most economical and reasonable scheme.

关键词

排水管道/管线改迁/临时排水

Key words

drainage pipe/pipeline relocation/temporary drainage