摘要

在喀斯特发育地区,桥梁钻孔灌注桩施工常出现漏浆、塌孔等现象,给施工带来困扰.为了减轻对周边复杂环境的影响,确保工程顺利进行,文章以白花特大桥为例,对喀斯特地区全护筒跟进超长桩基施工技术进行分析,该施工技术的成功应用取得了一定的社会效益和经济效益,可为今后同类工程提供指导.

Abstract

In the karst development area,the phenomenon of slurry leakage and hole collapse often occurs in the construction of bridge bored pile,which brings trouble to the construction.In order to reduce the impact on the surrounding complex environment and ensure the smooth progress of the project,this paper takes Baihua Bridge as an example to analyze the construction technology of full casing follow-up super-long pile foundation in karst area.The successful application of this construction technology has achieved certain social and economic benefits,which can provide guidance for similar projects in the future.

关键词

喀斯特地区/全护筒/桩基施工

Key words

karst area/entire casing/pile foundation construction