工程技术研究2024,Vol.9Issue(16) :205-207.DOI:10.19537/j.cnki.2096-2789.2024.16.066

双机组烧结余热发电主厂房结构设计方案选择

The Selection of Structural Design Scheme for Main Power House of Double-unit Sintering Waste Heat Power Generation

苗锋
工程技术研究2024,Vol.9Issue(16) :205-207.DOI:10.19537/j.cnki.2096-2789.2024.16.066

双机组烧结余热发电主厂房结构设计方案选择

The Selection of Structural Design Scheme for Main Power House of Double-unit Sintering Waste Heat Power Generation

苗锋1
扫码查看

作者信息

  • 1. 湖南中冶长天节能环保技术有限公司,湖南 长沙 410205
  • 折叠

摘要

为了适应生产发展的需要,钢企选择通过"新建一期,预留二期"的方式建设双机组烧结余热发电主厂房.文章通过工程实例,对以往该类厂房结构的分期建设方案进行了总结.针对不足之处,提出不受二期招标设备影响的主厂房同步建设方案.有效降低了施工难度,减少了投资,解决了实际问题.

Abstract

In order to meet the needs of production devel-opment,many steel enterprises choose to build the main power house of double-unit sintering waste heat power generation through the way of"building phase Ⅰ and re-serving phase Ⅱ".Through engineering examples,this pa-per summarizes the previous phased construction scheme of this kind of power house structure.In view of the short-comings,the synchronous construction scheme of the main power house which is not affected by the bidding equip-ment of phase Ⅱ is put forward.It effectively reduces the difficulty of construction,reduces investment,and solves practical problems.

关键词

余热发电主厂房/厂房结构设计/同步建设/钢筋混凝土框排架结构

Key words

main power house of waste heat power gen-eration/plant structure design/synchronous construction/reinforced concrete frame bent structure