双机组烧结余热发电主厂房结构设计方案选择
The Selection of Structural Design Scheme for Main Power House of Double-unit Sintering Waste Heat Power Generation
苗锋1
作者信息
- 1. 湖南中冶长天节能环保技术有限公司,湖南 长沙 410205
- 折叠
摘要
为了适应生产发展的需要,钢企选择通过"新建一期,预留二期"的方式建设双机组烧结余热发电主厂房.文章通过工程实例,对以往该类厂房结构的分期建设方案进行了总结.针对不足之处,提出不受二期招标设备影响的主厂房同步建设方案.有效降低了施工难度,减少了投资,解决了实际问题.
Abstract
In order to meet the needs of production devel-opment,many steel enterprises choose to build the main power house of double-unit sintering waste heat power generation through the way of"building phase Ⅰ and re-serving phase Ⅱ".Through engineering examples,this pa-per summarizes the previous phased construction scheme of this kind of power house structure.In view of the short-comings,the synchronous construction scheme of the main power house which is not affected by the bidding equip-ment of phase Ⅱ is put forward.It effectively reduces the difficulty of construction,reduces investment,and solves practical problems.
关键词
余热发电主厂房/厂房结构设计/同步建设/钢筋混凝土框排架结构Key words
main power house of waste heat power gen-eration/plant structure design/synchronous construction/reinforced concrete frame bent structure引用本文复制引用