抽水蓄能电站竖井上弯段混凝土施工技术研究
Research on Concrete Construction Technology of Shaft Upper Curved Section in Pumped Storage Power Station
韩飞1
作者信息
- 1. 中国水利水电第七工程局有限公司,四川 成都 610213
- 折叠
摘要
抽水蓄能电站竖井上弯段混凝土施工技术研究旨在探索高效、安全、可靠的混凝土施工新工艺.文章通过深入分析竖井上弯段的结构特点与施工难点,结合现场实际条件,提出了一系列优化措施,包括提高混凝土入仓质量、改进浇筑与振捣工艺、加强模板支撑与稳定性控制等.实际应用验证了文章采用的施工技术的可行性,提高了施工质量.
Abstract
The research on the concrete construction tech-nology of the shaft upper curved section of the pumped storage power station aims to explore an efficient,safe and reliable new concrete construction process.Through in-depth analysis of the structural characteristics and construction difficulties of the upper curved section of the shaft,combined with the actual conditions on site,this paper puts forward a series of optimization measures,including improving the quality of concrete warehous-ing,improving the pouring and vibrating process,and strengthening the formwork support and stability control.The practical application verifies the feasibility of the con-struction technology adopted in the paper and improves the construction quality.
关键词
混凝土施工技术/竖井上弯段/抽水蓄能电站/混凝土入仓Key words
concrete construction technology/shaft upper curved section/pumped storage power station/concrete warehousing引用本文复制引用
出版年
2024