云南水力发电2024,Vol.40Issue(2) :120-122.DOI:10.3969/j.issn.1006-3951.2024.02.028

环氧自流平在水电站厂房的施工技术分析

Analysis of Construction Technology for Epoxy Self leveling in Hydroelectric Power Plant Buildings

杨志虎
云南水力发电2024,Vol.40Issue(2) :120-122.DOI:10.3969/j.issn.1006-3951.2024.02.028

环氧自流平在水电站厂房的施工技术分析

Analysis of Construction Technology for Epoxy Self leveling in Hydroelectric Power Plant Buildings

杨志虎1
扫码查看

作者信息

  • 1. 云南华电金沙江中游水电开发有限公司梨园发电分公司,云南 丽江 674100
  • 折叠

摘要

厂房是水电站的主要组成部分,而地面是厂房重要的基础建筑,必须有着高标准的施工要求.环氧自流具有干净、整洁、耐压、耐腐蚀、防静电、易清洁等特点,可以很好的用于厂房地面大面积涂刷.以梨园水电站厂房地面为例,就环氧自流平大面积应用施工技术的主要措施和工艺进行阐述,为水电站厂房地面环氧自流平大面积施工提供经验.

Abstract

The factory building is the main component of a hydropower station,and the ground is an important foundation building for the factory building,which must have high standard construction requirements.Epoxy self leveling has the characteristics of cleanliness,tidiness,pressure resistance,corrosion resistance,anti-static,and easy cleaning,and can be well used for large-scale painting of factory floors.Taking the Liyuan hydropower plant as an example,this article elaborates on the main measures and processes of large-scale application of epoxy self leveling construction technology,providing experience for large-scale construction of epoxy self leveling on the ground of hydropower plant buildings.

关键词

环氧自流平/水电站/厂房地面/施工技术

Key words

epoxy self leveling/hydropower station/factory floor/construction technology

引用本文复制引用

出版年

2024
云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
参考文献量7
段落导航相关论文