砂石料延迟供应索赔案例分析

扫码查看
针对发包人材料供应时间滞后于合同约定时间而导致承包人提出的费用索赔问题,以云南省滇中引水工程某标段砂石料延迟供应索赔为例,提出首先确定补偿单价、然后计算应予以补偿的砂石料数量、最后确定补偿费用,分步骤计算索赔费用的工作思路,就区分工期责任、不区分工期责任、承包人承担固定数量或比例的砂石料供应责任 3 种砂石料补偿数量的计算方法展开分析,从发包人视角提出索赔事项的处理思路和注意事项.
Case Analysis of Delayed Supply Claim of Sand-gravel Material
In response to the cost claim issue raised by the contractor due to the delay in material supply by the employer compared to the agreed time in the contract,this paper takes a claim for delayed supply of sand and gravel materials in a certain section of the Dianzhong Water Diversion Project in Yunnan Province as an example,and proposes a work approach of first determining the compensation unit price,then calculating the amount of sand and gravel materials that should be compensated,and finally determining the compensation cost,and calculating the claim cost step by step.It analyzes the calculation methods of three types of compensation quantities for sand and gravel materials:distinguishing the responsibility for construction period,not distinguishing the responsibility for construction period,and the contractor assuming a fixed quantity or proportion of sand and gravel material supply responsibility.From the perspective of the employer,it proposes the handling ideas and precautions for compensation matters.

Dianzhong Water Diversion Engineeringsand and gravel materialsdelayed supplyclaim

李俊伟

展开 >

云南省滇中引水工程有限公司,云南 昆明 650051

滇中引水工程 砂石料 延迟供应 索赔

2024

云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
年,卷(期):2024.40(2)
  • 2