首页|防洪河道拓宽工程方案对比研究

防洪河道拓宽工程方案对比研究

扫码查看
研究针对石岩河防洪河道拓宽工程进行了方案研究.通过对河道现状及问题的分析,提出了向左岸拓宽和向右岸拓宽2种方案.通过比较分析,选择了向左岸拓宽方案,并进行了具体的方案设计.同时,讨论了拆迁和征地工作、上下游衔接和迁改高压线路的相关问题.最后,提出了施工计划和管理的重要性,并强调了质量控制、安全管理以及其他考虑因素.
Comparative Study on Flood Control River Widening Engineering Schemes
This paper conducts a scheme study on the widening project of the Shiyan River flood control channel.Through the analysis of the current situation and problems of the river,it proposes two options:widening towards the left bank and widening towards the right bank.Through comparative analysis,a widening plan towards the left bank was selected and a specific plan design was carried out.Meanwhile,this paper discusses issues related to demolition and land acquisition,upstream and downstream connections,and relocation of high-voltage power lines.Finally,it highlights the importance of construction planning and management,and emphasizes quality control,safety management,and other considerations.

Shiyan Riverflood controlriver widening

洪树星

展开 >

潮州市金桥中介服务有限公司,广东 潮州 521000

石岩河 防洪 河道拓宽

2024

云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
年,卷(期):2024.40(3)
  • 8