云南水力发电2024,Vol.40Issue(7) :67-71.DOI:10.3969/j.issn.1006-3951.2024.07.017

某大型水电站导流洞进口闸室结构三维有限元分析

Three-Dimensional Finite Element Analysis of Inlet Lock Chamber Structure of Diversion Tunnel in a Large Hydropower Station

鞠智敏
云南水力发电2024,Vol.40Issue(7) :67-71.DOI:10.3969/j.issn.1006-3951.2024.07.017

某大型水电站导流洞进口闸室结构三维有限元分析

Three-Dimensional Finite Element Analysis of Inlet Lock Chamber Structure of Diversion Tunnel in a Large Hydropower Station

鞠智敏1
扫码查看

作者信息

  • 1. 中国电建集团中南勘测设计研究院有限公司,湖南 长沙 410014
  • 折叠

摘要

某大型水电站导流洞进口闸室结构为一个典型的三维受力结构,特别是封堵期作用于闸门上的最大水头达到 120m,水推力大.为了保证导流洞进水口闸室结构在复杂受力情况下的安全可靠性,建立闸室整体有限元模型,并参考类似工程相关计算,主要对该导流洞进口闸室结构在完建期、运行期和封堵期 3 种工况进行三维计算分析.

Abstract

The inlet lock chamber structure of a large hydropower station diversion tunnel is a typical three-dimensional stress structure.The maximum water head acting on the gate during the sealing period reaches 120m,with a high hydraulic thrust.In order to ensure the safety and reliability of the intake lock chamber structure of the diversion tunnel under complex stress conditions,this paper establishes an overall finite element model of lock chamber.And referring to similar engineering calculations,it conducts three-dimensional calculation analysis on the inlet lock chamber structure of the diversion tunnel under three working conditions:completion period,operation period,and sealing period.

关键词

进口闸室/三维有限元/应力分析/大型水电站

Key words

inlet lock chamber/three-dimensional finite element analysis/stress analysis/large hydropower station