Application of Mud free Wall Protection Rotary Excavated Bored Pile in Slope Engineering
Taking the construction of anti slip piles on the side slope of the Laizihe Reservoir power plant as an example,this paper introduces the construction principle,construction process,construction operation points,construction quality control,and monitoring of the power plant slope of the slurry free retaining wall rotary excavation bored pile.The construction technology of mud free wall protection rotary excavation drilled pile has been successfully applied in the east slope project of Laizihe Reservoir Power Plant in Weining County,with good quality control and significant results.