缙蓄电站下库大坝填筑施工道路优化布置

扫码查看
在水电工程大坝填筑施工过程中,施工道路布置是前期施工准备工作中必不可少的一部分,需要考虑诸多因素.结合浙江缙云抽水蓄能电站下库面板堆石坝现场实际情况,从安全、经济、高效的原则出发,对下库大坝填筑施工道路进行详细规划,拟定了 3 个规划方案,并对 3 个方案进行对比分析,从而找出最优的大坝填筑道路规划方案,有效推动了工程的顺利建设.
Optimization and Layout of Construction Roads for the Filling of Lower Reservoir Dam of Jinyun Pumped Storage Power Station
During the construction process of dam filling in hydropower engineering,the layout of construction roads is an essential part of the preliminary construction preparation work,and many factors need to be considered.Based on the actual situation on site,this paper starts from the principles of safety,economy,and efficiency to carry out detailed planning of the construction road for the lower reservoir dam filling.Three planning schemes are formulated and compared to find the optimal dam filling road planning scheme,which effectively promotes the smooth construction of the project.

pumped storagedam fillingroad layoutcomparative analysis

董书礼

展开 >

中国水利水电第十四工程局有限公司,云南 昆明 650041

抽水蓄能 大坝填筑 道路布置 对比分析

2024

云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
年,卷(期):2024.40(9)