Time Control of Concrete Pumping Blockage Treatment Based on QC Group Activities
Based on the A3 project of Yizhao Expressway in Zhaotong City,Luozehe Extra Large Bridge is adopted QC group activities to carry out problem-solving group activities.By adopting a causal analysis diagram,the causes are analyzed from the aspects of human,machine,material,method,environment,and measurement,and targeted measures are proposed to address the factors that affect the treatment time of concrete pump blockage.It provides a guarantee for the continuity of the concrete of the Luoze River Grand Bridge,not only improving the construction quality of the concrete,but also ensuring the high-quality performance of the project.
Luozehe Extra Large BridgeQC grouppump blockageprocessing timecontinuity