首页|水库岸坡煤洞处理方案比选

水库岸坡煤洞处理方案比选

扫码查看
以楚雄市腊武地水库修建过程中遇到的人工洞穴问题为对象,研究了水库岸坡的处理方案及投资情况.腊武地水库选址于存在煤洞的位置,煤洞的存在可能导致岸坡稳定性受到影响,造成蓄水后岸坡垮塌和水库渗漏问题.为了解决这些问题,提出了不同的处理方案,最终选择了适当的煤洞处理方案,并进行了投资估算.研究结果强调了前期勘察工作的重要性.
Comparison and Selection of Treatment Plans for Coal Caves on Reservoir Bank Slopes
This paper focuses on the artificial cave problem encountered during the construction of Lawudi Reservoir in Chuxiong City,and studies the treatment plan and investment situation of the reservoir bank slope.The location of Lawudi Reservoir is located in a location with coal caves,which may affect the stability of the bank slope,leading to bank slope collapse and reservoir leakage after water storage.To address these issues,different solutions have been proposed.Finally,an appropriate coal mine treatment plan was chosen and an investment estimate was made.The research findings emphasize the importance of preliminary survey work.

bank slope stabilityhigh density electrical method testcave treatmentleakage problem

朱学俊、李杨林

展开 >

楚雄欣源水利电力勘察设计有限责任公司,云南 楚雄 675000

岸坡稳定性 高密度电法试验 洞穴处理 渗漏问题

2024

云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
年,卷(期):2024.40(z1)
  • 8