首页|进水口混凝土施工技术

进水口混凝土施工技术

扫码查看
水电站进水口工程是实现电站蓄水发电的关键项目,TB水电站进水口场地狭窄、坝体结构复杂、工序繁多、技术要求高、质量要求严是该项目的施工特点,同时TB水电站引水隧洞没有单独的施工支洞作为施工通道,必须要利用进水口作为施工通道给进水口坝段的施工也带来了极大的不便,通过对这些问题进行认真细致的研究,同时在借鉴其他工程成功经验的基础上,成功解决了TB水电站进水口坝段施工技术难题.
Construction Technology of Inlet Concrete
The water inlet project of a hydropower station is a key project for achieving water storage and power generation.The narrow inlet site,complex dam structure,numerous procedures,high technical requirements,and strict quality requirements of TB hydropower station are the construction characteristics of this project.At the same time,the diversion tunnel of TB hydropower station does not have a separate construction support tunnel as a construction channel,and the inlet must be used as a construction channel,which also brings great inconvenience to the construction of the inlet dam section.By studying these issues and drawing on successful experiences from other projects,this paper has successfully solved the technical difficulties in the construction of the inlet dam section of TB hydropower station.

TB power stationhydropower engineeringinlet dam sectionconstruction

孙启佑、张凡、陈璐、秦杰、杨庆美

展开 >

中国水利水电第十四工程局有限公司,云南 昆明 650041

TB电站 水电工程 进水口坝段 施工

2024

云南水力发电
云南水力发电工程学会

云南水力发电

影响因子:0.213
ISSN:1006-3951
年,卷(期):2024.40(z2)