The centrifugal compressor and three-phase asynchronous motor in the raw material air compressor has high installation hazard and safety risk.According to the lifting and installation practice of the raw material air compressor in a power plant,a comprehensive analysis was conducted on the selection and calculation of relevant parameters in the lifting process of centrifugal compressor and three-phase asynchronous motor,as well as the specific precautions on centering and alignment during the installation period.By strictly controlling the details of the installation data,it ensures that the unit can run stably for a long time after installation.
关键词
原料空压机/钢丝绳选择/吊车选型/三表法找正
Key words
raw material air compressor/selection of steel wire rope/crane selection/three-gauge method for alignment