10kV变配电室的电气安装质量控制策略研究
Research on Electrical Installation Quality Control Strategy for 10 kV Substation and Distribution Room
张东岳 1王大可 1许成龙1
作者信息
- 1. 淄博齐林电力工程有限公司周村分公司,山东淄博 255300
- 折叠
摘要
作为电力系统中最广泛使用的设备,对10 kV变配电室进行合理安装与质量管理可极大提高供电质量,延长电力设备使用寿命,确保用电安全.以山东省某高校新校区 10 kV变配电室电气安装项目为例,通过阐述该变配电室电气设备的布置要点,从安装前、安装中、安装后 3个方面,提出电气安装质量控制措施,以期为同类配电室安装工程提供一定参考.
Abstract
As the most widely used equipment in the power system,reasonable installation and quality management of the 10 kV substation and distribution room can greatly improve the quality of power supply,prolong the service life of power equipment,and ensure electricity safety.Taking the electrical installation project of a 10 kV substation in a new campus of a university in Shandong Province as an example,this paper elaborates on the layout points of the electrical equipment in the substation,and proposes quality control measures for electrical installation from three aspects:Before installation,during installation,and after installation,in order to provide certain reference for similar substation installation projects.
关键词
10kV变配电室/电气安装/电力系统Key words
10 kV substation and distribution room/electrical installation/power system引用本文复制引用
出版年
2024