水利与建筑工程学报2024,Vol.22Issue(6) :143-148.DOI:10.3969/j.issn.1672-1144.2024.06.020

乌东德水电站导流洞新型堵头抗剪槽(齿槽)布置优化研究

Optimization of the Layout of New-type Shear Groove(Tooth Groove)of the Diversion Tunnel Plug in Wudongde Hydropower Station

李娇娜 王科 王洁 林紫婕
水利与建筑工程学报2024,Vol.22Issue(6) :143-148.DOI:10.3969/j.issn.1672-1144.2024.06.020

乌东德水电站导流洞新型堵头抗剪槽(齿槽)布置优化研究

Optimization of the Layout of New-type Shear Groove(Tooth Groove)of the Diversion Tunnel Plug in Wudongde Hydropower Station

李娇娜 1王科 1王洁 1林紫婕1
扫码查看

作者信息

  • 1. 长江勘测规划设计研究有限责任公司,湖北 武汉 430010
  • 折叠

摘要

为了不破坏岩体及预先施工的大坝主帷幕,乌东德水电站导流洞采用了新型直柱形堵头代替传统扩挖楔形堵头,针对此直柱形堵头,采用三维数值模拟手段,通过选取无齿槽、有齿槽两种堵头,对围岩、堵头及二者接触面的应力、变形、塑性区分布特征及其渐进破坏过程进行分析,并对堵头齿槽数量开展敏感性研究.结果表明:直柱形堵头设置齿槽是必要的,且利用齿槽可明显提高封堵体的安全储备;不同齿槽数量堵头的安全系数在3.7~4.6 之间,采用4 齿槽方案安全系数增加幅度最为明显,当齿槽数量超过8 个以后,安全系数增加幅度将明显降低.通过优化提出"前宽后窄、前密后疏"的新型直柱形堵头抗剪槽布置方式.

Abstract

In order to prevent damage the rock mass and the pre-constructed main curtain of the dam,the diversion tunnel of the Wudongde Hydropower Station adopts a new type of straight cylindrical plug instead of the wedge-shaped plug.Its structural type and the safety of the shear groove(tooth groove)layout under high water head conditions are the key issues of the project.Therefore,this paper adopted the method of three-dimensional numerical simulation to analyze the stress,deformation,plastic zone distribution characteristics,and progressive failure process of the sur-rounding rock,plug,and the contact surface between them by selecting two types of plugs:without tooth groove and with tooth groove.Sensitivity studies are also conducted on the number of tooth grooves in the plug to obtain the influ-ence law of the number of tooth grooves on the safety of the plug,demonstrate the necessity of setting tooth grooves in the plug,comprehensively evaluate the overload capacity and safety reserve of the plug,and finally determine a rea-sonable number of tooth groove schemes.The research results show that it is necessary to set tooth grooves in the straight cylindrical plug,and the use of tooth grooves can significantly improve the safety reserve of the closure body.The safety coefficients of plugs with different numbers of tooth grooves range from 3.7 to 4.6,and the increase in safety coefficient is most significant when using the 4-tooth groove scheme.When the number of tooth grooves exceeds 8,the increase in safety coefficient will be significantly reduced.Through optimization research,this paper innovatively pro-poses a new type of straight cylindrical plug shear groove layout method of "wide front and narrow back,dense front and sparse back".

关键词

乌东德水电站/直柱形堵头/抗剪槽布置方式/受力分析/安全性评价

Key words

Wudongde hydropower station/straight cylindrical plug/shear groove layout/stress analysis/safety evaluation