并行大断面顶管下穿管线地表变形规律实测分析

扫码查看
为了探究并行大断面顶管近距离施工过程对地表沉降与上部管线变形的影响,依托广州市轨道交通三号线东延段海傍站的车站顶管工程,通过并行顶管施工全过程数据分析发现,顶管机顶进阶段应重点控制刀盘前后1 倍管节高度范围的土体沉降变形;后行顶管顶进阶段对地表和管线影响小于先行顶管顶进阶段,分别约占48。6%和51。04%;适时对中间段管节进行二次注浆,减小该段的地层损失,有效控制地表沉降与管线变形。
Field Measurement and Analysis of Surface Deformation Law of Parallel Large Section Pipe Jacking under Pipeline
In order to explore the influence of the short-distance construction process of parallel large-section pipe jacking on the surface settlement and the deformation of the upper pipeline,based on the station pipe jacking project of Haibin Station in the east extension section of Guangzhou Rail Transit Line 3,the data analysis of the whole process of parallel pipe jacking construction is carried out,and it is concluded that the soil settlement deformation in the range of 1 times the height of the pipe section before and after the cutterhead should be mainly controlled in the jacking stage of the pipe jacking machine.The influence of the later pipe jacking stage on the surface and pipeline is less than that of the first pipe jacking stage,accounting for 48.6%and 51.04%respectively.Timely secondary grouting of the middle section of the pipe section can reduce the formation loss of the section and effectively control the surface settlement and pipeline deformation.

parallel large section pipe jackingsurface subsidencepipeline deformationfield measurement

王增辉

展开 >

中水珠江规划勘测设计有限公司,广东广州 510635

并行大断面顶管 地表沉降 管线变形 现场实测

2024

广东交通职业技术学院学报
广东交通职业技术学院

广东交通职业技术学院学报

影响因子:0.315
ISSN:1671-8496
年,卷(期):2024.23(4)