盾构隧道下穿既有隧道保护方案优化分析

扫码查看
盾构下穿既有隧道会产生明显的扰动影响,存在较大施工风险,需要进行控制保护。依托某近距离下穿既有隧道的盾构隧道工程,建立了MJS水平加固、管棚注浆加固、地面袖阀管注浆加固3种方案的三维有限元模型,分析了不同加固方案下既有隧道的水平位移、竖向位移变化特征,并从变形控制、工法缺点、可实施性、费用方面进行了比较分析,确定了最优加固方案。研究结果表明:既有隧道以竖向位移为主,是变形控制关键指标;MJS水平加固对既有隧道位移控制效果最有利,地面袖阀管注浆加固效果最差;综合多方面因素,管棚注浆加固为最优保护方案;加固处理后土体强度得到改善,右线盾构隧道施工对既有隧道最大位移量和位置影响不大;双线开挖面距离在2。5倍洞径以上,施工扰动性可一定程度降低。结论可为相似下穿工程提供借鉴与参考。
Optimization Analysis of Protection Schemes for Shield Tunnel Undercrossing Existing Tunnel
The construction of shield tunnel has an obvious effect on the upper tunnel.There are significant construction risks and control and protection should be carried.Based on one shield tunnel undercrossing the existing tunnel,three-dimensional FEM models of three rein-forcement schemes,which are MJS horizontal reinforcement,pipe-shed grouting reinforcement and ground sleeve valve pipe grouting rein-forcement,are built.The horizontal and vertical displacement characteristics of the existing tunnels under three reinforcement schemes are ana-lysed in detail.And a comparative analysis was conducted from the aspects of deformation control,construction method shortcomings,feasi-bility,and engineering costs to determine the optimal reinforcement scheme.Some conclusions have been drawn.Firstly,the displacement of existing tunnels is mainly vertical displacement,which is the key index for tunnel deformation control.Secondly,displacement control of ex-isting tunnels,the scheme of MJS horizontal reinforcement is the best and ground sleeve valve pipe grouting reinforcement has the worst ef-fect.Thirdly,based on four factors,the scheme of pipe-shed grouting reinforcement.Fourth,the soil strength has been improved after rein-forcement treatment and the of the right tunnel construction has little effect on the size and position of maximum displacement.Finally,with the distance between the excavation faces of double tracks is more than 2.5 times the tunnel diameter,the construction disturbance can be re-duced to a certain extent.The conclusion can provide reference for similar undercrossing project.

new built tunnelexisting tunnelreinforcementMJS horizontal reinforcementpipe-shed grouting reinforcementsleeve valve pipe

龚云强、张委定、杨巧玲

展开 >

中国市政工程华北设计研究总院有限公司 天津 300074

天津市政工程设计研究总院有限公司 天津 300051

天津天狮学院 天津 301700

新建隧道 既有隧道 加固 MJS水平加固 管棚 袖阀管

2025

广东土木与建筑
广东省建筑科学研究院 广东省土木建筑学会

广东土木与建筑

影响因子:0.124
ISSN:1671-4563
年,卷(期):2025.32(1)