广州建筑2024,Vol.52Issue(5) :75-80.

横跨基坑大断面既有管线原位保护施工技术应用

Application of In-Situ Protection Construction Technology for Existing Pipelines Crossing Large Cross-sections of Foundation Pits

关丽娟 黄英志 李昕
广州建筑2024,Vol.52Issue(5) :75-80.

横跨基坑大断面既有管线原位保护施工技术应用

Application of In-Situ Protection Construction Technology for Existing Pipelines Crossing Large Cross-sections of Foundation Pits

关丽娟 1黄英志 1李昕1
扫码查看

作者信息

  • 1. 广州市盾建建设有限公司,广州 511400
  • 折叠

摘要

随着地铁建设在城市轨道交通蓬勃发展,不可避免需穿越密集建筑物及大型管线等,尤其是明挖车站或出入口施工时,经常会碰到地下管线保护问题.各类地下管线涉及产权单位多、拆改时间长、协调工作量大,往往由于局部管线未及时迁改,影响施工工期,浪费极大的人力、财力和物力.如遇到基坑下穿既有综合管廊,导致管线无法迁改的问题,则需要对综合管廊进行拆除,对管线进行原位保护.本文以实际工程为依托,通过分析国内外常规做法,针对综合管廊拆除和管线保护施工技术进行研究,采用钢板盒子成功解决了拆除综合管廊后内部管线保护的问题,并用承插笼平移法进行地连墙施工,保证了地连墙施工质量及深基坑的安全.实践结果表明,用本技术进行施工可以减少暗挖隧道的Φ400大管幕施工,减少钢材87t、水泥211t,相较于传统技术共节约了 562万元,工期可以节约15天,最大程度地减少因管廊涉及的权属单位较多、协调工作量大、造成无法迁改或迁改滞后给施工造成的严重损失,可为其他类似工程提供参考借鉴经验.

Abstract

With the booming development of subway construction in urban rail transit,it is inevitable to pass through dense buildings and large pipelines,especially during the construction of open cut stations or entrances and exits,underground pipeline protection issues are often encountered.Moreover,various types of underground pipelines involve multiple property rights units,take a long time to dismantle and modify,and require a large amount of coordination work.Often,due to the lack of timely relocation and modification of local pipelines,the construction period of the project is repeatedly delayed,wasting a great deal of manpower,financial resources,and material resources.If there is a problem where the foundation pit passes through the existing comprehensive pipe gallery,causing the pipeline to be unable to be relocated,it is necessary to dismantle the comprehensive pipe gallery and provide in-situ protection for the pipeline.Based on a real engineering project,analyzing common practices at home and abroad,research is conducted on the demolition and pipeline protection construction technology of the comprehensive pipe gallery.It successfully solves the problem of not relocating the comprehensive pipe gallery and internal pipe lines,allowing for normal excavation and construction of underground walls and deep foundation pits,ensuring the quality of underground wall construction and the safety of deep foundation pits.The practical results show that using this technology for construction can reduce the risk of underground tunnel excavation Φ The construction of400 large pipe curtains reduced 87 tons of steel and 211 tons of cement,saving a total of 5.62 million yuan compared to traditional technology.In terms of construction period,it can save 15 days,minimizing the involvement of more ownership units in the pipe gallery and the large coordination workload,resulting in inability to relocate or delayed relocation,causing serious losses to the construction itself.This can provide reference and experience for other similar projects.

关键词

管线原位保护/管廊分段切割/钢板盒子保护/管线悬吊

Key words

pipeline in-situ protection/segmented cutting of pipe gallery/steel plate box protection/pipeline suspension