水科学与工程技术2024,Issue(2) :57-60.DOI:10.19733/j.cnki.1672-9900.2024.02.15

高压输电线路工程线塔基础冲刷分析计算

Analysis and calculation of erosion on foundation of high voltage transmission line tower engineering

陈雅倩 赵国强
水科学与工程技术2024,Issue(2) :57-60.DOI:10.19733/j.cnki.1672-9900.2024.02.15

高压输电线路工程线塔基础冲刷分析计算

Analysis and calculation of erosion on foundation of high voltage transmission line tower engineering

陈雅倩 1赵国强1
扫码查看

作者信息

  • 1. 中工武大设计集团有限公司新疆分公司,乌鲁木齐 830000
  • 折叠

摘要

以新疆和田县矿产业园区基础设施建设项目220 kV输电线路的冲刷影响为例,当其布置与河流交叉时,涉及电力、水利规范的双重制约,对各类冲刷公式适用情况进行分析,确定适合的冲刷计算公式及冲刷计算结果,最终确定总冲刷深度为一般冲刷深度与局部冲刷深度之和,可为相关类似工程的评价提供参考.

Abstract

Taking the 220 kV transmission line of the infrastructure construction project in the Rare Earth Metal Industrial Park in Hetian County,Xinjiang as an example,when it is arranged to cross a river,it involves dual constraints of power and water conservancy regulations.This article analyzes the applicability of various erosion formulas and determines the suitable erosion calculation results and formulas.Ultimately,it determines the total erosion depth as the sum of general erosion depth and local erosion depth,providing reference for the evaluation of similar projects.

关键词

输电线路/穿河/冲刷计算

Key words

transmission line/river crossing/erosion calculation

引用本文复制引用

出版年

2024
水科学与工程技术
河北省水利学会 水利部河北水利水电勘测设计研究院

水科学与工程技术

影响因子:0.334
ISSN:1672-9900
参考文献量11
段落导航相关论文