首页|新建隧洞下穿爆破对公路隧道结构的影响:以温州市瓯江引水工程为例

新建隧洞下穿爆破对公路隧道结构的影响:以温州市瓯江引水工程为例

扫码查看
为了探寻爆源逐步接近既有隧道情况下衬砌受爆破振动的响应规律、爆破荷载作用下的应力分布状态,结合温州市瓯海区西山隧洞工程,根据施工现场爆破监测数据和数值模拟结果对新建隧道爆破施工时相交隧道的安全性进行研究.研究结果表明,振速主要受到爆心距和装药量的影响,爆心距越小,装药量越大,振速峰值越高;爆心距决定隧道衬砌合速度峰值发生位置;衬砌合速度峰值位置同时是最大拉应力点;随爆心距的缩进,危险点从拱腰位置移动到拱脚.
Influence of Under-pass Blasting Construction of Diversion Tunnels on Highway Tunnel Structures:Taking Xishan Tunnel Project in Ouhai District,Wenzhou City as an Example
In order to explore the response law of lining under blasting vibration and the stress distribution state under blasting load when the blasting source gradually approaches the existing tunnel,combined with the Xishan Tunnel Project in Ouhai District,Wenzhou City,the safety of intersecting tunnels during the construction of new tunnel blasting was studied based on the blasting monitoring data and numerical simulation results at the construction site.The research findings indicate that vibration velocity is primarily influenced by the distance to the blasting center and the amount of explosive charge used.Specifically,as the blasting center distance decreases and the amount of explosive charge increases,the peak vibration velocity becomes higher.The blasting center distance determines the location of the peak lining speed within the tunnel.Simultaneously,this peak speed location corresponds to the point of maximum tensile stress.As the blasting center distance decreases,the critical point shifts from the arch waist position to the foot of the arch.

tunnel engineeringnumerical simulationblasting constructioncross tunnel

王昊、庄一舟、陈俊清

展开 >

浙江工业大学土木工程学院,杭州 310014

中电建华东勘测设计研究院有限公司,杭州 310014

隧道工程 数值模拟 爆破施工 交叉隧道

2024

科学技术与工程
中国技术经济学会

科学技术与工程

CSTPCD北大核心
影响因子:0.338
ISSN:1671-1815
年,卷(期):2024.24(13)
  • 20