路基工程2024,Issue(3) :146-150.DOI:10.13379/j.issn.1003-8825.202401077

西瓦里克地质区域条件下软岩高边坡施工技术

Construction Technology of Soft Rock High Slope under the Condition of Siwalik Geological Region

胡天然 刘勇 陈很
路基工程2024,Issue(3) :146-150.DOI:10.13379/j.issn.1003-8825.202401077

西瓦里克地质区域条件下软岩高边坡施工技术

Construction Technology of Soft Rock High Slope under the Condition of Siwalik Geological Region

胡天然 1刘勇 1陈很1
扫码查看

作者信息

  • 1. 中铁二局集团有限公司,成都 610032
  • 折叠

摘要

以尼泊尔某水电工程引水隧道TBM始发平台永久边坡工程为依托,介绍西瓦里克地质区域条件下软岩高边坡的设计方案与施工关键技术,通过稳定性计算,采用土钉锚杆+网格梁/喷锚支护+综合排水措施.通过施工监测结合永久监测数据分析,边坡整体稳定,满足设计要求.

Abstract

Based on the permanent slope project of TBM starting platform of water diversion tunnel of a hydropower project in Nepal,this paper introduces the design scheme and construction key technologies of soft rock high slope under the condition of Siwalik geological region.Through stability calculation,soil nail bolt+grid beam/spray anchor support+comprehensive drainage measures are adopted.Through construction monitoring combined with permanent monitoring data analysis,the overall stability of the slope is achieved,meeting the design requirements.

关键词

多雨气候/复杂软岩/TBM/高陡台阶/弧形边坡/变形监测/锚固支护/生态环保/稳定性

Key words

rainy climate/complex soft rock/TBM/high-steep step/curved slope/deformation monitoring/anchorage support/eco-environment protection/stability