路基工程2024,Issue(5) :228-233.DOI:10.13379/j.issn.1003-8825.202402030

海底隧道穿越断层破碎带突涌水防治关键技术

Key Technologies for Sudden Water Inrush Prevention and Control in Submarine Tunnels crossing Fault Fracture Zones

蔡世康 陈耀 任文锋
路基工程2024,Issue(5) :228-233.DOI:10.13379/j.issn.1003-8825.202402030

海底隧道穿越断层破碎带突涌水防治关键技术

Key Technologies for Sudden Water Inrush Prevention and Control in Submarine Tunnels crossing Fault Fracture Zones

蔡世康 1陈耀 1任文锋1
扫码查看

作者信息

  • 1. 中铁二局集团有限公司,成都 610091
  • 折叠

摘要

胶州湾第二海底隧道工程受张扭性裂隙影响,其地下水极其发育、地质条件复杂,通过突涌水超前地质预报预警及超前注浆防治两个方面,介绍海底隧道穿越断层破碎带突涌水防治关键技术在胶州湾第二海底隧道工程中的应用.

Abstract

The second undersea tunnel project in Jiaozhou Bay is affected by tensile-torsional fissures,and its groundwater is extremely developed and the geological conditions are complicated.Through the two aspects of advance forecast and early warning of sudden water influx and advance forecast and grouting prevention and control,it introduces the application of the key technology of sudden water influx prevention and control for the undersea tunnel crossing the fault fracture zones in the second undersea tunnel project in Jiaozhou Bay.

关键词

海底隧道/钻爆法/穿越断层/突涌水/超前预报/注浆加固/风险控制

Key words

undersea tunnel/drilling and blasting method/crossing faults/sudden water inrush/advance forecast/grouting reinforcement/risk control