首页|深中通道中山大桥主桥超宽大节段钢箱梁吊装匹配技术

深中通道中山大桥主桥超宽大节段钢箱梁吊装匹配技术

扫码查看
深中通道中山大桥主桥为主跨580 m的双塔双索面钢箱梁斜拉桥,主梁采用流线型扁平钢箱梁,梁宽46 m(含风嘴),主梁共划分69个节段,标准段长18 m、最大吊重约429 t,采用桥面吊机双悬臂吊装.由于钢箱梁节段自重大、宽度较大、横桥向竖向刚度较小等,在桥面吊机悬臂吊装过程中,会出现钢箱梁匹配面高差过大(最大约63 mm)的问题.为解决该问题,实现梁段精确匹配安装,提出3种钢箱梁吊装匹配方案:"门架+拉索"方案、"牛腿反力架"方案、"一字梁锁定+C形焊缝+部分张拉斜拉索"方案.经有限元仿真分析综合比选,最终选择"一字梁锁定+C形焊缝+部分张拉斜拉索"方案.该方案以箱梁竖腹板为定位点,提前焊接一字梁,采用法兰连接后锁定待拼梁段,部分焊接拼接面内箱梁形成C形焊缝;通过提前挂索并张拉部分斜拉索,减小匹配面已拼梁段横桥向竖向变形,达到箱梁匹配要求.施工中采取了匹配高差调节、局部应力控制、拼接缝宽控制等关键技术,最终将该桥钢箱梁匹配面高差减小至9.8 mm以内,钢箱梁局部应力可控,斜拉索初张过程中钢箱梁应力增量小于10 MPa,且各箱梁节段拼接缝宽可控制在1 cm以内.
Hoisting and Matching Techniques for Large Steel Box Girder Segments of Main Bridge of Zhongshan Bridge of Shenzhen-Zhongshan Link
The main bridge of Zhongshan Bridge forming a part of the Shenzhen-Zhongshan Link is a cable-stayed bridge with a main span of 580 m.The stay cables are fanned out in double cable planes.Measured 46 m in width(with wind fairings),the superstructure consists of streamlined flat steel box girders.To facilitate construction,the steel box girders were fabricated into 69 segments that could be erected by balanced cantilever method using deck cranes,with typical segment length of 18 m and maximum hoisting weight of 429 t.The steel box girder segments are heavy and wide,but owes relatively small vertical stiffness across bridge width,as a result,the elevation difference of two adjacent segments is big once they are placed into position,and the maximum elevation difference reaches about 63 mm.To achieve precise matching of steel box girder segments,three solutions were proposed,including the solution of using portal frames and stays,the solution of using bracket reaction frame,and the solution of using cross beams for locking,C-shaped welds and tensioning partial stay cables.In accordance with the finite element analysis,the last solution was finally selected.Taking the vertical web of the box girder as the anchor point,the cross beam was welded in advance,and then connected with a flange,afterwards the girder segment waiting for placement was locked.Subsequently,the girder segment was partially welded with the already-placed girder segment,forming C-shaped welds.To reduce the vertical deformation across bridge width of the already-placed girder segment and reach the matching precision of the segments,the stay cables suspending the next waiting-segment were installed and tensioned to a degree.During the construction,the elevation difference of adjacent girder segments was tuned,local stresses were monitored and the seams between adjacent girder segments were controlled,as a result,the elevation differences of the matching surfaces of the adjacent girder segments were controlled less than 9.8 mm,the local stresses in the steel box girder were under good control,during the initial tensioning of the stay cables,the stress increment of the steel box girder was less than 10 MPa,and the seams between adjacent girder segments were less than 1 cm.

cable-stayed bridgestreamlined flat steel box girderbalanced cantilever erectionhoisting and matchingelevation difference of matching surfacesscheme selectionfinite element methodconstruction technique

宋神友、李小祥、鲁立涛、刘健、朱超宇

展开 >

深中通道管理中心,广东 中山 528400

上海同济检测技术有限公司,上海 200092

斜拉桥 流线型扁平钢箱梁 双悬臂架设 吊装匹配 匹配面高差 方案比选 有限元法 施工技术

广东省重点领域研发计划项目

2019B111106002

2024

桥梁建设
中铁大桥局集团有限公司

桥梁建设

CSTPCD北大核心
影响因子:1.428
ISSN:1003-4722
年,卷(期):2024.54(1)
  • 19