首页|湖杭高铁富春江特大桥主桥施工关键技术

湖杭高铁富春江特大桥主桥施工关键技术

扫码查看
湖杭高铁富春江特大桥主桥为(30+46+300+97+62.395)m 4线无砟轨道高低塔斜拉桥,桥塔采用H形钢-混组合结构,中跨及桐庐侧次边跨部分主梁为钢-混结合梁,其余区域主梁为预应力混凝土箱梁.主桥2号和3号墩基础采用先围堰后平台的方案施工,塔梁同步施工.针对该桥施工难点,2号墩采用水下预裂爆破整平、先围堰后平台、冲击钻引孔+回转钻成孔的组合方式成孔等技术,保证了钻孔桩成孔质量,提高了作业工效;采用塔梁同步施工,实现了快速化施工;主梁采用钢管+贝雷梁+盘扣支架法现浇、支架法滑移架设+原位拼装相结合及浮吊悬臂拼装等施工技术,缩短了主梁架设工期;无砟轨道施工期间,通过建立CPⅢ控制网、主梁温度敏感性分析、主梁刚度修正、调索、底座板厚度调整、自密实混凝土厚度调整等对施工过程线形进行控制,实现了无砟轨道线形精准控制.
Key Construction Technique of Main Bridge of Fuchunjiang River Bridge of Huzhou-Hangzhou High-Speed Railway
The main bridge of Fuchunjiang River Bridge of Huzhou-Hangzhou High-speed Railway is an extradosed bridge carrying four ballastless tracks.The bridge is arranged in five spans of 30,46,300,97 and 62.395 m,where the superstructure in the 62.395 m-long span on the Tonglu side consists of steel trough girders and concrete slabs,and the superstructure in the remaining spans is composed of prestressed concrete box girders.The construction of the pylons and the superstructure was carried out in parallel to accelerate the construction.During the construction of the foundations of piers No.2 and No.3,the trestles and boring platforms were sequentially installed after the steel cofferdams were in sound condition.A boring technique was tailored for the pier No.2 to ensure the boring quality and efficiency,including the specific steps of underwater pre-split blasting leveling,constructing steel cofferdam ahead of boring platform,and the borehole was made using impact driver for first-phase boring and the rotary drill for borehole formation.The main girders were cast on the scaffolds formed of steel pipes,bailey trusses and a ringlock scaffolding system,and erected on site by the combined utilization of sliding on scaffolds,in-place assembly,and cantilever assembly conducted by barge-mounted cranes,as a result,the erection schedule was shortened.The alignment of the ballastless tracks were accurately controlled by a series of measures,including building a CP 111 control network,thermal sensitivity analysis of main girders,main girder stiffness modification,cable tuning,thickness adjustment for base plates and the adjustment of the thickness of the self-compacting concrete.

high-speed railwaycable-stayed bridgeballastless tracksloping bedrock without overburdensynchronized pylon and girder constructionalignment controlconstruction technique

潘成杰

展开 >

沪杭铁路客运专线股份有限公司,上海 200070

高速铁路桥 斜拉桥 无砟轨道 无覆盖层倾斜岩面 塔梁同步施工 线形控制 施工技术

2024

桥梁建设
中铁大桥局集团有限公司

桥梁建设

CSTPCD北大核心
影响因子:1.428
ISSN:1003-4722
年,卷(期):2024.54(6)